Judge rules Massachusetts offshore wind project ha…


BOSTON (AP) — A federal judge said Tuesday that a nearly completed Massachusetts offshore wind project can continue, as the industry successfully challenges the Trump administration in court.

At U.S. District Court in Boston, Judge Brian Murphy halted the administration’s stop work order for Vineyard Wind, citing the potential economic losses from the delays and the developers’ likelihood of success on their claims. Vineyard Wind is one of five big offshore wind projects on the East Coast that the Trump administration froze days before Christmas, citing national security concerns— and the fourth that has since been allowed to go forward.

Developers and states sued seeking to block the administration’s order. Prior to Vineyard Wind’s hearing, federal judges had allowed three of the five to restart construction: the Revolution Wind project for Rhode Island and Connecticut by Danish company Orsted, the Empire Wind project for New York by Norwegian company Equinor, and Coastal Virginia Offshore Wind for Virginia by Dominion Energy Virginia. Those three judges essentially concluded that the government did not show that the national security risk is so imminent that construction must halt, said Carl Tobias, a University of Richmond Law School professor who has been following the lawsuits.

Orsted is also suing over the administration halting its Sunrise Wind project for New York— the fifth paused project — but has not had a hearing yet.

Vineyard Wind is a joint venture between Avangrid and Copenhagen Infrastructure Partners, located 15 miles (24 kilometers) south of Martha’s Vineyard and Nantucket, Massachusetts. It is 95% complete and partially operational, able to produce nearly 600 megawatts of power for the New England electric grid, according to the complaint. Before the pause, it was on track to be complete by the end of March, with 62 turbines generating a total of 800 megawatts. That is enough clean electricity to power about…